Lower Stair

The building materials supplier had promised hemlock stair parts would be delivered two days before our target completion date. Eric, the finish carpenter, was ready to install the stair in a day. Then, they flaked out on us, saying it would be two more weeks. We needed Plan B.

We found that MacBeath Hardwood had clear, vertical-grain douglas fir in stock in rough 4/4 thickness. So, we bought a couple of hundred board feet of the material and planned to set up our own mill to make the flooring, treads, and risers.  MacBeath delivered the material to the job site in FOUR HOURS. The wood was beautiful and mostly in 14-16′ lengths. Had I known how nice this material was, I would have used it for door/window casing too. (However, it was expensive…about $6/bf for the rough material.)

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s